Foundation Testing

Pile Integrity Test (PIT/PET)

Low-strain testing that checks the continuity and integrity of cast-in-situ piles.

Overview

A light hammer blow on the pile head generates a stress wave whose reflections are recorded and interpreted. Discontinuities such as necking, cracks or changes in section show up in the signal, allowing many piles to be screened quickly and non-destructively.

A light hammer tap at the pile head sends a stress wave down the pile. Reflections from changes in section or quality come back and are recorded. Reading those reflections shows the pile length and flags necking, cracks, voids or contamination, without any damage to the pile.

  • Non-destructive, low-strain method
  • Detects major defects and changes in section
  • Quick screening of large numbers of piles
  • Reported per pile

Key Benefits

Quick screening

Dozens of piles can be checked in a day.

No damage

Non-destructive, so the pile stays fully usable.

Early defect detection

Problems are found before the pile cap is cast and loaded.

Low cost

A practical check for every pile on a project.

Where It Is Used

  • Cast-in-situ bored piles
  • Driven cast-in-situ piles
  • Quality assurance on bridge and building foundations
  • Checking piles after installation problems

How We Work

  1. 1

    Prepare the pile head

    Clean and level the head to expose sound concrete.

  2. 2

    Attach the sensor

    Place an accelerometer on the pile head.

  3. 3

    Tap with the hammer

    Record several blows and average the signals.

  4. 4

    Interpret

    Identify pile length and any anomalies, then report per pile.

What You Receive

  • Signal record for each pile
  • Estimated pile length
  • Anomaly notes with depth
  • Summary report

Key Projects

Pile integrity test: key projects

Selected projects with client, consultant and contractor.

Frequently Asked Questions

How soon after casting can piles be tested?

Typically after the concrete has gained enough strength, commonly a few days to a week, in line with the project specification.

Does it show pile capacity?

No. It checks integrity. Capacity needs a load test.